Build your pay system · Plan your project

Settle scope, data and responsibility first. The analysis comes second.

Most pay transparency projects stall on questions nobody answered at the start. Four decisions and five phases keep yours moving.

Four scoping questions

01

Which legal entities?

Decide which companies in the group are in scope and who reports for each.

02

Which employee groups?

Collectively agreed, non-tariff, executives, apprentices – include or exclude each on purpose.

03

Which pay components?

Base, variable, allowances and benefits in kind. The Directive counts all of them.

04

How ambitious?

Minimum compliance, or a pay system you can explain to every employee.

Five phases, each with its result

  1. 01

    Scope and mandate

    Project order, sponsor and roles agreed.

  2. 02

    Data and job inventory

    One dataset, gaps prioritised.

  3. 03

    Job evaluation and groups of equal work

    A documented comparison logic.

  4. 04

    Analyse and decide

    A prioritised list of actions, including progression rules.

  5. 05

    Embed

    A process for information requests, an annual reporting cycle, an annual neutrality check.

Phases 2 and 3 run in parallel – the groups of equal work decide which data you need.

Who does what

Role groupWhoTheir job
Steer and decideManagement board; HR project leadMandate, budget, sign-offs; scope, pace, escalation
Shape and multiplyWorks council, finance, legal; managers, internal communicationsCo-determination, data, legal review; translate, listen, keep messages consistent
Understand and askEmployeesKnow what changes, why and when; questions and feedback flow back

Where you start decides how long it takes

Typical ranges for a mid-sized organisation; size, number of entities and data quality move them.

Typically 3–6 months

A grading structure exists

Check the grading logic, clean the data, validate groups of equal work.

Typically 6–12 months

Some structure, data gaps

Close data gaps, complete and harmonise the job architecture.

Typically 9–18 months

Collective scales plus non-tariff roles without a structure

Define the evaluation logic, build job architecture and grading.